How to Deliver Work in Agile Sprints

Six questions, asked in order, to go from a long plan that slips to something usable every two weeks.

An agile sprints playbook is a six-stage sequence that defines what customers value, orders the work, sets up Scrum, runs two-week sprints, handles interruptions and measures the result.

Agile sprints playbook: six stages in order, from Lean Core Principles and User Story Mapping through the Scrum Framework and the sprint cycle to the Priority Matrix and KPIs.

The route

Six questions, in order

The route runs from what customers value to a team that delivers it every two weeks: what matters, what to build first, who decides, how each sprint runs, what happens to interruptions, and how you know it works.

On timing: stages 1 to 3 take about two weeks, before the first sprint. Stage 4 starts the sprints; stages 5 and 6 begin in the first month.

Scope fixed and a date that can't move? The project planning playbook fits better.

Free tools run each stage on your own team's work. The Agile Project Management Tool lays out all six stages and starts you off; or start at stage 1 with the Lean Principles Tool, or take the 15-minute guided tour first.

  1. What do customers value?Stage 1 · Lean Core Principles

    Passes on: value in one sentence, and where the time goes

    Can't say what customers value?Ask them before building anything.

  2. What should we build first?Stage 2 · User Story Mapping

    Passes on: a thin first release, and an ordered backlog

    Backlog already small and ordered?Go straight to stage 3.

  3. Who decides what?Stage 3 · Scrum Framework

    Passes on: three accountabilities filled, and a Definition of Done

    Nobody can say no to requests?Name a Product Owner first.

  4. What happens in each sprint?Stage 4 · The Agile Sprint Cycle

    Passes on: a two-week rhythm, and a Sprint Goal each time

    Work can't wait for fixed cycles?Use Kanban instead.

  5. What about urgent requests?Stage 5 · Priority Matrix

    Passes on: a rule for every interruption

  6. Is it working?Stage 6 · Key Performance Indicators

    Passes on: a few measures, each with an owner

    Velocity used as a target?Stop; it will inflate.

  7. Is it still working?Then · Review the measures every quarter

The example

One team, followed all the way through

This playbook follows one team from start to finish. It is an illustrative composite, and the details are simplified.

A chain of 40 hardware stores in Monterrey, Mexico, is building online ordering with same-day delivery. Its customers are building contractors and homeowners. An in-house team of eight builds it: five developers, a designer, a tester and the e-commerce manager.

The work started as a nine-month plan with 60 features. Four months in, it is behind, nothing has been released, and store managers send the team new requests every day. The owner wants something customers can use every few weeks instead.

Each stage below ends with what the team produced at that step, so you can watch one stage's output become the next stage's input.

Stage 1 of 6

What do customers value, and where does work wait?

Tool: Lean Core Principles · Time: a week, most of it interviews

Agile methods grew out of lean thinking, and the five lean principles explain what sprints are for. Start with the first two; the other three are what the sprints will deliver.

The five lean principles

1Value
Defined by the customer, for a specific product at a specific price
2Value stream
Every step taken to deliver that value, including the waiting
3Flow
The steps run continuously, without batches or queues
4Pull
Work starts only when the next step signals it is ready
5Perfection
Go back to the first principle and round again

Value has no tool, which is why it gets assumed. Ask customers, not the sales team. Then follow one finished piece of work from request to release, and count the days it was worked on against the days it waited. The gap is usually large, and it is made of batches: work held until a set is ready to hand on.

One feature, reordering a past order, from request to release (illustrative). The highlighted row is the batch that held it longest.
StepDays waitingDays worked
Approved by the steering group9–
Designed62
Built84
Tested, with everything else in the release122
Released4–
Total: 47 days398

What goes inInterviews with 8 to 12 customers, and the dates one recent piece of work moved through each step.

What comes outWhat customers value, in one sentence, and where a typical piece of work spends its time.

Skip it if: the team already delivers small pieces often and knows what customers value.

Handed to stage 2: value in one sentence, “the right parts on site before noon, at a time contractors can trust”, and a feature that spent 39 of its 47 days waiting.

Decision point

If nobody can say what customers value without guessing, ask them before building anything. Here, the plan's 60 features centered on product photos and reviews; the 12 contractors interviewed cared about the delivery time and whether the part was in stock.

Stage 2 of 6

What should we build first?

Tool: User Story Mapping · Time: a 1-day workshop

A plan of 60 features is a list. A story map puts the work in the order a customer meets it. Across the top runs the backbone: the activities a customer moves through, in sequence. Under each activity go the smaller pieces of work, the user stories, most valuable at the top.

Then cut across the map. The first release is the walking skeleton: the thinnest version in which a customer can get from one end of the backbone to the other. It should feel slightly inadequate. What people learn from using it usually changes the later slices.

The backbone and the first cut across it (illustrative). The highlighted row is the step the old plan had left until last.
Backbone activityWalking skeleton (release 1)Later releases
Find the partSearch by namePhotos, filters, reviews
Check it is in stockStock at the nearest storeStock across all 40 stores
Order and payCard payment onlyAccount credit for contractors
Choose a delivery timeOne morning windowHourly windows
Receive it on siteA text message when the van leavesLive tracking

What goes inThe value statement from stage 1, and the existing feature list and requests.

What comes outA backbone, a first release that works end to end, and the backlog ordered behind it.

Skip it if: the backlog is already small, ordered and agreed.

Handed to stage 3: a backbone of five activities, a walking skeleton of 14 user stories, and the rest of the 60 features ordered behind it.

Decision point

If a customer can't get from one end of the backbone to the other, the first release is a subset, not a slice. The old plan would have shipped search and photos first, which no contractor could use to get a part delivered.

Stage 3 of 6

Who decides what, and what counts as done?

Tool: Scrum Framework · Time: 2 to 3 days to agree, then from the first sprint

Scrum is a short framework: three accountabilities, three artifacts, and five events, which stage 4 covers. An accountability says who answers for what. An artifact is a shared record the team works from, kept where everyone can see it. Since 2020, each artifact carries a commitment, named beside it below.

The two halves of the table below don't pair up row by row. The Product Owner looks after the Product Backlog. The Developers own the Sprint Backlog and build the Increment. The Scrum Master owns none, and helps the others use them.

Two parts matter most at the start. The Product Owner orders the backlog and must be able to say no, including to senior people. And the Definition of Done stops work being called finished when it is only built. In Scrum, the designer and tester count as Developers too: everyone doing the work.

Scrum's accountabilities and artifacts, filled in for the team (illustrative). The highlighted row was the hardest to agree.
KindPartWhat it is forIn the example
AccountabilityProduct OwnerThe product's value, and the order of the backlogThe e-commerce manager, with authority to turn down store requests
AccountabilityScrum MasterThe team's effectiveness, and removing what blocks itThe tester, given half her time for it
AccountabilityDevelopersA usable piece of product every sprintThe five developers, the designer and the tester
ArtifactProduct Backlog, with its Product GoalOne longer-term aim the backlog is ordered against“Contractors order online and get parts on site before noon”
ArtifactSprint Backlog, with its Sprint GoalOne reason this sprint is worth runningSet at each Sprint Planning
ArtifactIncrement, with its Definition of DoneWhat finished meansReviewed by a second developer, tested on a phone, live at one store, help page updated

What goes inThe ordered backlog from stage 2, and the people available.

What comes outA name for each accountability, a Product Goal, and a Definition of Done.

Skip it if: never. It is where authority over the backlog gets settled.

Handed to stage 4: the e-commerce manager as Product Owner, a Product Goal in one sentence, and a four-part Definition of Done.

Decision point

If the Product Owner can't say no to senior people, the backlog will be ordered by whoever asks loudest. The owner put the e-commerce manager's authority in writing and told the store managers before the first sprint.

Stage 4 of 6

What happens in each sprint, and how long does it take?

Tool: The Agile Sprint Cycle · Time: two weeks per sprint, from now on

The sprint cycle is Scrum's five events in order. Each has a timebox, a maximum length, which is a ceiling, not a target.

Refinement, preparing the next items so they can be planned, has no slot of its own and gets skipped. Give it about a tenth of the team's time. The table follows the team's third sprint through every event.

Scrum's events in a two-week sprint, and what happened in the team's third sprint, which put the walking skeleton live (illustrative). The highlighted row is where customers first used it.
EventTimeboxIn the team's third sprint
Sprint PlanningUp to about 4 hoursDay 1, 90 minutes. Sprint Goal: “Contractors near two pilot stores can order, pay and choose the morning delivery.” Six user stories chosen
Daily Scrum15 minutesEvery morning. On day 4, the payment test account wasn't ready; the Scrum Master got it that afternoon
Refinement (not an event)About a tenth of the team's timeDay 6, 1 hour: next sprint's user stories split to fit two days each
Sprint ReviewUp to about 2 hoursDay 10. Two contractors and three store managers place real orders; a request for site directions joins the backlog
Sprint RetrospectiveUp to about 1.5 hoursDay 10, 1 hour: keep testing each user story the day it is built
The SprintTwo weeksFive of six user stories done and the Sprint Goal met; the sixth went back to the backlog

What goes inThe ordered backlog, the roles from stage 3, and a sprint length.

What comes outA Sprint Goal and a usable Increment every sprint.

Skip it if: never, once you have chosen sprints.

Handed to stage 5: a sprint every two weeks, and the walking skeleton live at two stores after the third.

Decision point

If Sprint Planning keeps running its full timebox, fix refinement, not the meeting. The first planning took five hours; with refinement twice a week, the third took 90 minutes.

Stage 5 of 6

What happens to requests that arrive mid-sprint?

Tool: Priority Matrix · Time: a 2-week log, then a rule for every request

A sprint protects the team's plan for two weeks, but urgent requests still arrive. The Priority Matrix, also called the Eisenhower Matrix, sorts them by two questions. Is it important: what happens if it is never done? Is it urgent: what happens if it waits until next sprint? Each of the four answers has its own action.

Log every request for two weeks and sort them together. Most misplacing is seniority standing in for consequence: a request from a director reads as important, and the same one from a store clerk doesn't. The matrix is for interruptions, not for ordering the backlog; that was stage 2. The grid below sorts the 64 requests store managers sent the team in two weeks.

UrgentNot urgent
ImportantNot important
Do: 6 requestsCheckout fails; wrong prices onlineFixed now, by one developer on duty each week. The only kind that interrupts the sprint
Schedule: 21 requestsA new product categoryInto the backlog, for the Product Owner to order
Delegate: 29 requests“When will my store go live?”Answered by the stores' support desk
Delete: 8 requestsA weekly report nobody openedStopped

What goes inEvery request that reached the team over two weeks, with who sent it.

What comes outA rule for each kind of request, and a small part of each sprint kept free for the urgent ones.

Skip it if: requests rarely arrive between sprints.

Handed to stage 6: a developer on duty for the six urgent fixes, a support desk answering the 29 status questions, and sprints that kept their goals.

Decision point

If most requests land in Do, check who sent them, not just what they say. In the team's first sort, 19 requests were in Do; after asking what would happen if each waited two weeks, six were left.

Stage 6 of 6

How do you know it is working?

Tool: Key Performance Indicators · Time: half a day to set up, then a monthly look

A measure becomes an indicator when it has a target and an owner who can move it. Sort candidates into four types first, because each type has a different reader.

The four types of performance measure

1Key result indicator
How the business did overall; for the board
2Result indicator
What several teams produced between them
3Performance indicator
What one team can be held to
4Key performance indicator
The few measures that move everything else

Measure outcomes for customers and the flow of work, not activity. Velocity, the amount of work a team finishes per sprint, is a planning aid for the team itself. Made a target, it inflates: the estimates grow and nothing else does.

The team's measures, at the start and after six months (illustrative). The highlighted row is the one the whole route aimed at.
MeasureTypeOwnerStartSix months
Orders on site before noonKey performance indicatorHead of logistics–92%
Online orders a weekResult indicatorProduct Owner0640
Days from request to releasePerformance indicatorScrum Master4712
Sprint Goals met, last six sprintsPerformance indicatorDevelopers–5 of 6

What goes inThe value statement from stage 1, the Product Goal from stage 3, and the team's own data.

What comes outFour or five measures, each with a type, an owner and a target, reviewed monthly.

Skip it if: never. Without it, nobody can say whether the switch worked.

Handed on: four measures with owners and targets, a monthly review, and velocity kept inside the team.

Decision point

If a measure has no owner who can move it, it is a fact, not an indicator. “Online sales” was dropped as a team measure because pricing and stock, which drive it, sit outside the team.

Pace

Fast track or thorough

The fast track suits one small team trying sprints for a quarter. The thorough run suits a team replacing a long plan that has gone wrong, as in the example. The order of the stages stays the same either way.

What changes between the two paces.
StageFast track (a few days)Thorough (about two weeks)
1. Lean Core PrinciplesA value statement and one feature's timelineCustomer interviews, and several features traced
2. User Story MappingBackbone and first slice in an afternoonA full map with the people who know each step
3. Scrum FrameworkNames against the three accountabilitiesProduct Owner's authority in writing; Definition of Done agreed
4. The Agile Sprint CycleTwo-week sprints with all five eventsThe same, with refinement time protected
5. Priority MatrixA rule for urgent fixesA two-week log, sorted, with a rule for each quadrant
6. Key Performance IndicatorsTwo measures with ownersFour or five, typed, owned and reviewed monthly

Failure modes

How agile switches go wrong

Common failures and what prevents them.
What happensWhat it looks likeThe fix
The old plan cut into two-week piecesSprints that finish nothing a customer can useMap the backbone; release a walking skeleton first
A Product Owner without authorityThe backlog reordered by whoever asked lastPut the authority in writing, and tell people
Done means builtWork “finished” that fails in testing laterA written Definition of Done
Every request treated as urgentSprint Goals missed, sprint after sprintSort requests; only the Do quadrant interrupts
Velocity as a targetEstimates grow; delivery doesn'tMeasure customer outcomes and time to release

After the playbook

Is it still working?

Lean's fifth principle is to go round again. Each retrospective changes one thing; every quarter, look at the measures from stage 6 and trace one recent feature from request to release again, as in stage 1.

In the example, a feature took 12 days from request to release after six months, against 47 at the start. The next waiting point was outside the team: the steering group's monthly approval meeting, now replaced by the Product Owner's call.

Common questions

Agile sprints: quick answers

How do you switch a team to agile sprints?

Agree what customers value and see where work waits now. Map the work as a customer meets it and release a thin version that works end to end first. Name a Product Owner who can say no, write a Definition of Done, then run two-week sprints with all five Scrum events. Sort interruptions so only real emergencies break a sprint, and track a few measures with owners.

What are the three accountabilities in Scrum?

The Product Owner, answerable for the product's value and the order of the backlog; the Scrum Master, answerable for the team's effectiveness; and the Developers, everyone who does the work, answerable for a usable Increment every sprint.

How long should a sprint be?

A month or less, by the Scrum Guide. Two weeks is the most common choice: long enough to finish something usable, short enough to change course often. Keep the length fixed once chosen.

What is a walking skeleton?

The thinnest first release in which a user can get from one end of the journey to the other, with one option where there will later be many. It should feel slightly inadequate; what people learn from using it shapes the later releases.

How do you handle urgent requests during a sprint?

Sort them by importance and urgency. Only urgent and important ones, such as a broken checkout, interrupt the sprint, handled by a person on duty. Important ones go into the backlog, and urgent but unimportant ones go to someone else.

Should velocity be used as a KPI?

No. Velocity helps a team plan its own sprints. Used as a target, it grows through bigger estimates rather than more delivered. Measure outcomes for customers and the time from request to release instead.

What is the difference between agile sprints and a project plan?

A project plan fixes the scope and works out the date. Sprints fix the rhythm and let the scope change as people learn. Sprints suit work where needs shift; a plan suits a fixed scope and a fixed date.