Work Breakdown Structure Tool

Break what your project must produce into work packages, each small enough to estimate and with one owner, and test every branch against the 100% rule, so no work turns up halfway through.

What the project must deliver

  • Start with what the project has to produce, not with a task list.
  • One line is enough: every branch below is tested against it.

Branches and work packages

  • A branch is one main part of what the project produces, such as a fitted store or a trained team.
  • Under each, the work packages: pieces small enough to estimate, give to one owner and track.
  • Name each by what it produces (Approved drawings), not by an action (Draw the plans).
  • Build it with the people who will do the work.
Or paste a list you already have

One item per line. A line with no indent is a branch; an indented line, or one starting with a dash or a number like 1.2, is a work package under it. An owner can follow a tab or " | ".

Your plan never leaves your browser

The branch and package names, the owners and the scope stay on your computer and in your progress file. To write the diagnosis, only the counts are sent to our server, by place in your list. How it works

About the tool

Why it exists

All the work, before any of it is scheduled

Projects rarely finish late because a known task took too long. They finish late because of work nobody listed: an approval, an inspection, a contract that takes three weeks to sign. A work breakdown structure lists everything the project must produce, level by level, and tests that nothing is missing. This tool builds one with you, checks it against the three rules, and keeps it as a file you can come back to.

It works on its own, and as stage 1 of our playbook for planning a project that finishes on time, where the work packages and their owners go on to the critical path.

The method

How the tool works

Two levels. Branches are the main parts of what the project produces; work packages are the pieces under each, small enough to estimate, give to one owner and track as a unit. Most projects of a few months need 15 to 40 packages.

The 100% rule. The pieces under any item add up to all of its scope, no more and no less. Only the people doing the work can judge that, so the tool asks it of each branch, with what "done" means for the branch written beside it, and lets you add what is missing right there. The step's tips list the kinds of work first lists often miss: outside approvals, permits, inspections, contracts with long lead times, customs, testing, training, handover.

Nouns, not verbs. A package names something the project produces ("Sofas ordered"), so everyone can tell when it is finished. A name that starts with an action ("Order the sofas") gets a suggested noun form, which you can use or ignore.

One owner each. Every package needs one named person. A package with no owner, or with two, is flagged, and the owners' package counts are shown, because the busiest owners are where clashes start.