FreeNo sign-upYour plan stays on your computer

Resource Allocation Matrix Tool

Put each person's project work and everything else they do in one grid, week by week. See who is booked over 100% in the busy weeks, and settle each clash by moving work that has float.

The people

  • Everyone the project needs, by name or role. Contractors who do nothing else for you can be left out.

Who works on the project's activities

  • Each cell is the share of that person's time the activity takes while it runs: 50 means half their week.
  • The weeks come from the plan in the earlier stage.

Their work outside the project

  • Day-to-day work, other projects, anything else that claims their time, as a share of their week.
  • Give the weeks it runs, counted from the project's start; leave them empty for every week.

Your plan never leaves your browser

The names of people, activities and other work stay on your computer and in your progress file. To write the diagnosis, only the loads and weeks are sent to our server, by place in your list. How it works

About the tool

Why it exists

Nobody booked on two things at once

A project plan assumes everyone is free when it needs them. They rarely are: the same people run the day-to-day work and often another project, and the weeks when everything lands are where promises break. A resource allocation matrix puts each person's claims in one grid, week by week, so the clashes show while there is still time to move things.

It works on its own, and as stage 4 of our playbook for planning a project that finishes on time, where it takes the schedule from the earlier stages and only moves work that has float.

The method

How the tool works

The grid. People down one side; across the top, the work claiming them: the project's activities at their scheduled weeks, and the work outside the project in the weeks it runs. Each cell is a share of the person's week; a row adds up to their load.

Week by week. Activities are placed at their earliest starts from the plan. An activity that runs for part of a week counts for that part. The busiest week is the worst person's peak, not the average.

Clashes and the 80% line. Over 100% is a clash. Over 80% is flagged: people planned at 100% have no room for illness, meetings or anything else.

Moving work. An activity with float can start later by up to its float without moving the finish; the tool recalculates the plan with each move, and warns if the finish moves. "Suggest moves" tries starting work with float later, one move at a time, when it lowers a clash without creating another; "Undo the suggested moves" puts the starts back as they were.

Before and after. The tool keeps each person's peak from when you first saw the clashes, and shows where each one ended up.

What leaves your computer. Names stay in your browser and your progress file. To write the diagnosis, the page sends our server only the loads and weeks, by place in your list, and the server keeps nothing.