PERT Calculator

Give each uncertain activity three estimates: optimistic, most likely and pessimistic. Get the expected finish, how sure it is, and the odds of making your date, path by path.

The date, and what finishing late costs

  • The time available counts from when the work starts.
  • What finishing late costs is optional: a penalty, lost sales, a missed season. With it, the results weigh what buying time costs against the lateness it saves.
Count time in

Three estimates for each uncertain activity

  • Ask the people who will do the work, not the person who wants it done.
  • Optimistic: if everything goes right. Pessimistic: if the usual things go wrong, not the worst you can imagine.
  • Activities on or close to the critical path are ticked. Give any other activity three estimates too if it is uncertain: tick it.

Your plan never leaves your browser

The activity names stay on your computer and in your progress file. To write the diagnosis, only the durations, the odds and the costs are sent to our server, by place in your list. How it works

About the tool

Why it exists

How likely the date really is

A plan built on one duration per activity says when the project finishes if everything takes as long as it usually does. It rarely does, and delays pile up along a path, not cancel out. PERT asks for three estimates instead of one, and turns them into an expected finish and the odds of making the date, so you can buy time while it is cheap instead of finding out in the last month.

It works on its own, and as stage 3 of our playbook for planning a project that finishes on time, where it takes the critical path from stage 2 and passes the plan and its buffer on.

The method

How the tool works

Expected duration. (O + 4M + P) ÷ 6, from the optimistic, most likely and pessimistic estimates. With 8, 10 and 18 weeks, the expected duration is 11 weeks. Activities with one estimate keep it, with no spread.

Spread. The standard deviation is (P − O) ÷ 6: 1.7 weeks for 8 and 18. Along a path, expected durations add, and so do the squares of the standard deviations; the square root of the total is the path's spread.

The odds. For each path from start to finish, the chance of finishing by the date comes from the normal distribution. When two paths could each finish last, both must finish on time, so the tool multiplies their odds. A path that mostly shares its uncertain activities with one already counted rises and falls with it, so it isn't counted twice.

Buying time. The tool keeps the estimates you first saw the odds with, and shows what each change did to the expected finish and the odds. With the cost of finishing late, it compares what the change cost with the lateness it is expected to save.

The buffer. The plan's dates use the most-likely durations. The gap between that finish and the date is the buffer; PERT's expected finish says roughly how much of it to expect to use.

What leaves your computer. The activity names stay in your browser and your progress file. To write the diagnosis, the page sends our server only the durations, the odds and the costs, by place in your list, and the server keeps nothing.