PERT Calculator
Give each uncertain activity three estimates: optimistic, most likely and pessimistic. Get the expected finish, how sure it is, and the odds of making your date, path by path.
This tool also runs as a stage in a playbook, which takes you through several tools in order:
- Plan a project that finishes on time Stage 3 of 6: how likely are you to finish by the date? Start at stage 1
Not following the playbook?
The date, and what finishing late costs
- The time available counts from when the work starts.
- What finishing late costs is optional: a penalty, lost sales, a missed season. With it, the results weigh what buying time costs against the lateness it saves.
Three estimates for each uncertain activity
- Ask the people who will do the work, not the person who wants it done.
- Optimistic: if everything goes right. Pessimistic: if the usual things go wrong, not the worst you can imagine.
- Activities on or close to the critical path are ticked. Give any other activity three estimates too if it is uncertain: tick it.
Other activities, with plenty of float
Your plan never leaves your browser
The activity names stay on your computer and in your progress file. To write the diagnosis, only the durations, the odds and the costs are sent to our server, by place in your list. How it works
The odds of making the date
A single duration is a guess that looks like a fact. With three estimates, the delays that pile up along a path show, and so does a second path almost as long as the critical one. If the odds are lower than you can accept, buy time on the critical path now, while it is cheap.
What odds can you accept?
A date with a penalty or a fixed opening usually needs four in five or better.
Buy time on the paths that count
Change the estimates of an activity you can speed up, with more people, money or a different way of doing it. Speeding up an activity off these paths buys nothing.
The odds of making the date
The paths that count
The critical path, re-estimated
The least certain activities
The buffer
Save your progress
Download your progress file to continue from this point any time, on any computer: choose it under "Coming back?" at the start of the tool. Each new file includes everything so far, including the earlier stages when they are connected, so keep the latest one. Your work stays in this browser only until you close it.
Not saved yet.
Take your results with you
A PDF of your odds of finishing on time, the paths that count, every estimate, the buffer, and the diagnosis.
About the tool
Why it exists
How likely the date really is
A plan built on one duration per activity says when the project finishes if everything takes as long as it usually does. It rarely does, and delays pile up along a path, not cancel out. PERT asks for three estimates instead of one, and turns them into an expected finish and the odds of making the date, so you can buy time while it is cheap instead of finding out in the last month.
It works on its own, and as stage 3 of our playbook for planning a project that finishes on time, where it takes the critical path from stage 2 and passes the plan and its buffer on.
The method
How the tool works
Expected duration. (O + 4M + P) ÷ 6, from the optimistic, most likely and pessimistic estimates. With 8, 10 and 18 weeks, the expected duration is 11 weeks. Activities with one estimate keep it, with no spread.
Spread. The standard deviation is (P − O) ÷ 6: 1.7 weeks for 8 and 18. Along a path, expected durations add, and so do the squares of the standard deviations; the square root of the total is the path's spread.
The odds. For each path from start to finish, the chance of finishing by the date comes from the normal distribution. When two paths could each finish last, both must finish on time, so the tool multiplies their odds. A path that mostly shares its uncertain activities with one already counted rises and falls with it, so it isn't counted twice.
Buying time. The tool keeps the estimates you first saw the odds with, and shows what each change did to the expected finish and the odds. With the cost of finishing late, it compares what the change cost with the lateness it is expected to save.
The buffer. The plan's dates use the most-likely durations. The gap between that finish and the date is the buffer; PERT's expected finish says roughly how much of it to expect to use.
What leaves your computer. The activity names stay in your browser and your progress file. To write the diagnosis, the page sends our server only the durations, the odds and the costs, by place in your list, and the server keeps nothing.