Critical Path Calculator

List the activities, how long each takes and what each must wait for. Get the critical path that sets the finish date, the float on everything else, and whether the plan fits the time you have.

The time you have

  • Count from when the work starts, after planning. A store opening in 22 weeks, with two weeks of planning, has 20 for the work.
  • A start date is optional: with one, the results show calendar dates.
Count time in

The activities

  • One duration each, the most likely. Stage 3 asks for a range.
  • Waits for: the letters of the activities that must finish first, such as B, C. Leave it empty if it can start at once.
  • Question the arrows as you go: many "waits for" are habits, not needs.

Or paste activities from a spreadsheet

Three columns: the activity, its duration and what it waits for (the letters of earlier rows, or their names). Copy the rows from Excel or Google Sheets and paste them here.

Your plan never leaves your browser

The activity names stay on your computer and in your progress file. To write the diagnosis, only the durations, the float and the time available are sent to our server, by place in your list. How it works

About the tool

Why it exists

The chain of work that sets the finish date

Every project has one chain of dependent work that takes longer than any other. The project can't finish before that chain does, so its length is the shortest the project can be, and a delay anywhere on it delays the finish. Everything else has float: time it can slip without moving the date. This tool finds the chain, the float on everything else, and whether the plan fits the time you have.

It works on its own, and as stage 2 of our playbook for planning a project that finishes on time, where it takes stage 1's work packages and passes the critical path on to PERT.

The method

How the tool works

The forward pass. Each activity can start once everything it waits for has finished: its earliest start is the latest of those finishes. Its earliest finish adds its duration. The project's length is the latest earliest finish.

The backward pass. Working back from the end, each activity's latest finish is the earliest of the latest starts of the activities waiting for it. Its latest start subtracts its duration.

Float. The gap between latest and earliest start, also called slack. Activities with zero float form the critical path. Activities with little float, a tenth of the project or less, are listed as close behind: they are the next to become critical.

Questioning the arrows. Step 2 lists every arrow on the critical path, so you can ask whether each activity really must wait for all of the one before. The tool keeps the network as you first drew it, and shows what each change did to its length.

Units and dates. Count in weeks or working days, with up to two decimals. With a start date, earliest starts are shown as dates; working days skip Saturdays and Sundays, not public holidays.

What leaves your computer. The activity names stay in your browser and your progress file. To write the diagnosis, the page sends our server only the durations, the float and the time available, by place in your list, and the server keeps nothing.