Playbook

How to Speed Up a Slow Business Process

Four questions, asked in order, for work that takes far too long.

A process speed-up playbook is a four-stage sequence of operations tools that finds where a process spends its time waiting, fixes the step holding everything up, and keeps the gain.

Process speed-up playbook: four stages in order, from value stream mapping and the Theory of Constraints to a Kaizen Blitz and a Kanban board.

The route

Four questions, in order

Slow processes are rarely slow because people work slowly. Most of the time, work is waiting. This playbook finds where it waits, fixes the one step that holds everything up, and keeps the queue from building again. Three points on the route can send you elsewhere.

On timing: stages 1 and 2 take two to three weeks. Stage 3 is a five-day event with a month of follow-up. Stage 4 starts during that event and then runs every day. When the first constraint is fixed, the next one appears, and you go back to stage 2.

  1. Where does the time go?Stage 1 · Value Stream Mapping

    Passes on: every step's working time and waiting time, on one page

    Mostly errors, not waiting?Use Lean Six Sigma instead.

  2. Which step holds everything up?Stage 2 · Theory of Constraints

    Passes on: the constraint, and how to get more through it

    The constraint is a rule?Change the rule. No event needed.

  3. How do you fix that step quickly?Stage 3 · Kaizen Blitz

    Passes on: a tested change to the constraint, running as the new standard

    The gain faded within a month?Find what slipped back before moving on.

  4. How do you stop work piling up again?Stage 4 · Kanban

    Passes on: a board with limits that keeps work flowing

  5. What happens when the next step slows?Then · Measure lead time, then repeat from stage 2

The example

One process, followed all the way through

This playbook follows one process from start to finish. It is an illustrative composite, and the details are simplified.

A mid-sized bank in Almaty, Kazakhstan, takes 34 days on average to approve a mortgage. Its two largest competitors take about ten. Customers who are approved elsewhere first simply withdraw. The head of retail lending has been asked to cut the time in half without hiring more staff. Every department believes its own step is fast, and each one is right about its own part.

Each stage below ends with what the bank produced at that step, so you can watch one stage's output become the next stage's input.

Stage 1 of 4

Where does the time go?

Tool: Value Stream Mapping · Time: 1 to 2 weeks

Start by drawing the whole process on one page, from request to delivery. Value Stream Mapping records every step and, under each one, two numbers: how long someone works on the item, and how long it waits before that step.

Get the numbers from real items, as the card below explains. Then add up the two rows separately. The gap between them is the point of the exercise: in most office processes, work fills less than a tenth of the time.

This map is the current state. Value Stream Mapping goes on to a future state and a plan to reach it; here, stages 2 to 4 are that plan.

Three Value Stream Mapping terms

LLead time
Total time from start to finish, as the customer sees it
PProcess time
Time someone is actually working on the item
WWaiting time
Lead time minus process time: the item sits in a queue

How to follow real items through

The ruleTime what happened, not what people say usually happens

  1. PickTen to thirty recent items, of the normal kind, not the problem cases
  2. RecordThe date and time each one arrived at each step, and when work on it started and stopped
  3. CheckWalk the process with the people who do each step, and ask where items wait and why
The mortgage process, mapped (illustrative). Lead time is about 34 days, of which about 9 hours is process time. The outlined cell is the longest wait.
StepIntakeDocument checkCredit scoringProperty valuationCredit committeeContract and payoutTotal
Waiting before the step–4 days3 days14 days5 days8 days34 days
Working time1 hour2 hours1 hour3 hours30 minutes90 minutes9 hours

What goes inA sample of real items followed through the process, start to finish.

What comes outEvery step's working and waiting time, with both totaled.

Skip it if: the process has two or three steps and the stall is obvious.

Handed to stage 2: 34 days of lead time holding about 9 hours of work. More than a third of the waiting sits in front of one step: property valuation.

Decision point

If the problem is mostly errors and rework, not waiting, use a different tool. Lean Six Sigma targets defects and variation. This playbook targets delay. Here, rework explained only a small share of the time, so the route went on.

Stage 2 of 4

Which one step holds everything up?

Tool: Theory of Constraints · Time: 2 to 3 days

Every process has one step that limits how much gets through, the constraint. Theory of Constraints says that speeding up any other step changes nothing: work simply waits longer in front of the constraint. So find it, and focus there.

The map from stage 1 usually points to it: the step with the longest queue in front of it. Three signs, seen together, confirm it. A step with a long queue that is not always busy is usually waiting on something else, so keep looking.

Three signs that confirm the constraint

1The longest queue
Work piles up in front of it
2Starved steps after it
People further on wait for work to arrive
3Always busy
It never runs out of work, even on quiet days

Then work through the Five Focusing Steps, in order. The order matters. Adding people or money comes fourth, after getting the most out of what is already there.

The Five Focusing Steps: Identify, Exploit, Subordinate, Elevate, Repeat

1Identify
Find the constraint: valuation, with 14 days of queue
2Exploit
Get the most from it: order the valuation on day 1, not after the document check
3Subordinate
Make other steps serve it: the document team works through files in the order their valuations are booked, so no valuer waits for paperwork
4Elevate
Add capacity only now: a second valuation firm
5Repeat
Find the next constraint once this one moves

Sometimes the constraint isn't a step at all, but a rule: a committee that meets once a week, or a sign-off nobody remembers the reason for. A rule can be changed in a meeting.

What goes inThe value stream map from stage 1.

What comes outThe constraint, named, with a plan for each of the Five Focusing Steps.

Skip it if: never. Without it, effort goes into steps that won't change the lead time.

Handed to stage 3: the constraint is property valuation. The bank starts with Exploit: ordering the valuation on the first day, alongside the document check rather than after it.

Decision point

If the constraint is a rule, change the rule. No improvement event is needed. Here the constraint was real work, but the next one, a credit committee that meets weekly, turned out to be a rule.

Stage 3 of 4

How do you fix that step quickly?

Tool: Kaizen Blitz · Time: a five-day event, with two weeks of preparation and a month of follow-up

A Kaizen Blitz is a short, focused improvement event, usually five days, in which a team from every function the step touches scopes, measures, tests and puts in place a change to one process before the week ends.

Point it at the constraint and nothing else. Change is tested on real work during the week, not argued about in meetings. By Friday, the new way is written down as the standard, with an owner.

Most gains from these events fade within months, because people drift back to the old way once attention moves on. So the event's real end is a check 30 days later: is the new standard still being followed, and is the measure still better?

Choose the team with care: the people who do the constraint step, one person from the step before and after it, and someone with the authority to change a form or a rule on the spot. Six to eight people is enough.

The bank's week (illustrative).
DayWhat happened
MondayScope agreed: valuation only. The team of six walked ten live files from intake to valuation
TuesdayFound why valuations waited: they were ordered only after the document check passed
WednesdayTested ordering valuations on day 1 for twelve new files
ThursdayFixed the forms valuers kept sending back, and agreed what happens if a file later fails
FridayNew standard written, owner named, 30-day check booked

What goes inThe constraint and the Exploit and Subordinate plans from stage 2.

What comes outA tested change to the constraint, written down as the new standard, with an owner.

Skip it if: the fix is obvious and small. Make it, and go to stage 4.

Handed to stage 4: valuation waiting fell from 14 days to 5, and was still at 5 at the 30-day check. Average lead time fell from 34 days to about 25.

Decision point

If the gain fades within a month, find what slipped back before moving on. A second event on a new constraint, on top of a gain that is fading, wastes both.

Stage 4 of 4

How do you stop work piling up again?

Tool: Kanban · Time: set up during the event, then daily

A fixed constraint stays fixed only if work stops piling up in front of it again. Kanban makes the flow visible on a board, with one column for each step, and puts a work-in-progress limit on each column: the most items that may sit there at once.

When a column is full, the step before it stops pushing work in and helps clear the queue instead. Work is pulled forward when there is room, not pushed when the earlier step finishes. That is what keeps queues short, and it shows the next constraint as soon as it appears: the column that is always full.

Set each limit at about the number of items in that column today, then lower it a step at a time. Hold a short daily meeting at the board, and start with the column that is at its limit.

1Document check

  • 14 filesIn progress

Limit 20

2Valuation

  • 15 filesFull: no new files pulled in

Limit 15

3Credit committee

  • 22 filesWaiting for the next meeting

Limit 25

4Contract

  • 9 filesIn progress

Limit 20

What goes inThe new standard from stage 3, and the steps from the stage 1 map.

What comes outA board with a limit on every column, reviewed by the team every day.

Skip it if: the process is so small that one person can see every item at once.

Handed on: the valuation column is at its limit, so the document team stops starting new files until a place opens up. The credit committee column is close to its limit most weeks: the next constraint.

Pace

Fast track or thorough

The fast track suits a small team and a short process. The thorough run suits a process that crosses several departments, where nobody sees the whole flow. Either way, the order of the stages stays the same; only the depth changes.

What changes between the two paces.
StageFast track (about a week)Thorough (6 to 8 weeks)
1. Value Stream MappingFive items followed on a whiteboardThirty items timed, across departments
2. Theory of ConstraintsThe longest queue, by eyeQueues measured for two weeks
3. Kaizen BlitzA two-day sessionA full five-day event with a 30-day check
4. KanbanA whiteboard with limitsA shared board for every step

Failure modes

How process speed-ups go wrong

Common failures and what prevents them.
What happensWhat it looks likeThe fix
Speeding up the wrong stepA faster step, and no change in lead timeFind the constraint first
Mapping from memoryA tidy map that matches nobody's real dayFollow real items through
Hiring firstMore staff, and the queue moves elsewhereExploit and subordinate before you elevate
Declaring victory on FridayThe old way back within weeksCheck the standard after 30 days
Stopping at one constraintOne fix, then the gains stallRepeat from stage 2 with the next one

After the playbook

Measuring lead time, then repeating

Track lead time every week, from the customer's point of view, as one of your KPIs. For the bank, the measure that mattered was the share of mortgages approved within 14 days, which rose from 4% to 31% in the first quarter.

Then repeat from stage 2. The Five Focusing Steps end with Repeat for a reason: once one constraint moves, another step becomes the limit. At the bank, the next one was the weekly credit committee, a rule, fixed by letting it approve smaller loans between meetings.

Keep the map from stage 1 up to date as you go. Redraw it after each constraint is fixed: the waiting moves, and the new map shows where it went.

Common questions

Process speed: quick answers

What is value stream mapping used for?

To see a whole process on one page, from request to delivery, with the working time and the waiting time of every step. It shows where work waits, which is usually where most of the time goes, and it is the first step in deciding what to fix.

What is a work-in-progress limit?

The most items allowed in one step of a process at once, shown at the top of a column on a Kanban board. When a column is full, the step before it stops sending work and helps clear the queue. Limits keep queues short and make the next bottleneck visible early.

How long does a kaizen blitz take?

The event itself usually runs five days. Allow about two weeks before it to scope the problem and collect data, and a check 30 days after it to confirm the new way is still being followed. A smaller problem can be handled in a two-day version.

How do you speed up a slow business process?

Find where the time actually goes, then fix the one step that holds everything up. Map the process with working and waiting time for each step, find the constraint, fix it in a short focused event, and use a Kanban board with limits to stop work piling up again.

What is the difference between lead time and process time?

Lead time is the total time from start to finish, as the customer sees it. Process time is the time someone is actually working on the item. The difference is waiting time, and in most office processes it is far larger than the work itself.

What is a bottleneck in a process?

The step that limits how much work gets through, called the constraint in the Theory of Constraints. It usually has the longest queue in front of it. Speeding up any other step doesn't shorten the lead time, because work simply waits longer in front of the bottleneck.

What are the Five Focusing Steps?

Identify the constraint, exploit it by getting the most out of it, subordinate other steps to its needs, elevate it by adding capacity, and repeat when the constraint moves. Adding capacity comes fourth, after the cheaper steps.

Should I use Lean Six Sigma or Theory of Constraints?

It depends on the problem. If the process is slow because work waits, start with Theory of Constraints. If it is slow because of errors and rework, Lean Six Sigma, which targets defects and variation, is the better fit.

How do you stop process improvements from fading?

Write the new way down as the standard, give it an owner, and check it 30 days later. A Kanban board with work-in-progress limits also helps, because it makes a growing queue visible before it becomes a delay.